E-Logistics (P) Ltd. and Anr. vs Financial Technologies (India) Ltd.
Oppression and Mismanagement-Existence of arbitration clause-The grievances of the petitioner styled as acts of oppression and mismanagement within the affairs of the company could not be adjudicated in proceedi [LexDoc Id : 321408]
Rattan Singh Associates (P) Ltd. vs Gill Power Generation Co. (P) Ltd. and Anr.
Arbitration-Interim measures by Court, Stay on invocation of bank guarantee-The petitioner could not seek a stay against the invocation of the bank guarantee under s.9 of the Arbitration and Conciliation Act 1996 on the ground [LexDoc Id : 317757]
Shanti Devi and Ors. vs Delhi Development Authority and Ors.
Curtailment of contractual construction work-Non-exculpatory clause-An appeal against rejection of a reasonable and bona fide claim arising out of damages caused due to curtailment of contractual construction work was [LexDoc Id : 309656]
HC (Delhi)
2006
Morgan Securities and Credit (P) Ltd. vs Modi Rubber Ltd.
Provisions of SICA 1985-Existence of non-obstante clause-An appeal under SICA 1985 to BIFR against permission granted by High court to borrower-respondent company to dispose off certain shares of the company [LexDoc Id : 305790]
Alankar Global (P) Ltd. and Ors. vs Dinesh Kumar Mathur and Ors.
Rejection of reference to arbitration-No provision to split cause of action-An application to refer subject matter of a suit to arbitration was rejected because all the parties to the suit were not parties to the arbitration a [LexDoc Id : 309660]